TCN restores Aba–Itu 132kV transmission line after 30-hour outage

The company announced in a statement issued in Abuja on Monday that electricity transmission through the line resumed at 7:53 p.m. on November 8.
According to TCN, the outage began at 1:02 p.m. on November 7 following a fault on the transmission line.
It said its maintenance crew subsequently patrolled the affected line and carried out the necessary repairs, leading to its successful restoration.
“Following the restoration, Port Harcourt Electricity Distribution Company (PHEDC) has resumed the off-take of electricity for onward distribution to customers in Uyo, Eket, Ekim and Itu.”
The company assured electricity consumers of its continued commitment to the efficient transmission of bulk electricity.
( NAN)

Metro6 days ago“Nigeria Cannot Afford To Fail In 2027” — UNOWAS Urges Peaceful Elections As NHRC Warns Against Electoral Offences
Special Report6 days agoCocaine: KC Luxury asks judge to withdraw from his trial over missing affidavit – The Witness Nigeria
Special Report4 days agoNamibia President hails Dangote’s $2.5bn investment as historic milestone for African industrialisation – The Witness Nigeria
Headlines4 days ago‘Politics is expensive everywhere’ – Wike replies critics over high billboard cost in Abuja
Metro4 days ago“Any Algorithm Can Calculate, But It Cannot Care” — NMCN Registrar Warns Nurses Against Overreliance On AI
Headlines7 days agoInaccurate information, algorithmic bias undermine justice – Kaduna Attorney-General warns young lawyers
Special Report5 days agoPolice invite late singer, Toluwanisings’s wife, father, as parties sign peace deal – The Witness Nigeria
Headlines6 days agoKayode Akinmade: Abiodun’s road revolution – From forgotten communities to connected economic corridors